HomeConstruction sectorSignum 93 Building · HCC Constructores

Design, substation and CCTV at the Signum 93 Building

A turnkey project for HCC Constructores: Series 3 design, utility permitting, a 300 kVA substation, electrical installations, CCTV and security and control, all under a single contract.

Construction · Signum 93 Building · HCC Constructores

What was needed

HCC Constructores needed the electrical, telecommunications and security scopes at Signum 93 to advance in step with the construction programme. Contracting them separately is what usually creates the classic bottleneck: a finished building that cannot be energised because the application was filed late or what was built does not match what was approved.

Design series
Series 3
Substation
300 kVA
Scope
Electrical + CCTV + security
Contract type
Turnkey
Scope

What we did

  • Electrical design Series 3 with drawings, calculation reports and load schedules.
  • Utility permitting through to approval.
  • Installation of a 300 kVA substation.
  • Electrical installations throughout the building.
  • System of CCTV, security and control.
Technical background

Why integrated contracting avoids the bottleneck

The classic electrical delay on a project does not happen during construction: it happens at the end. The structure is up, the finishes are done, and the building cannot be energised because the application was filed late, or because what was built does not match the approved design and the network operator asks for corrections.

That problem is born of fragmented contracting. When one engineer does the design, another company builds it and nobody owns the permitting, every comment opens an argument about whose fault it is while the programme runs on. With a single contract that grey area disappears: whoever designed it built it and answers to the operator for it.

FAQ

Answers to common questions

When should the design be filed with the network operator?
As early as possible. Depending on the size of the project and the operator's workload, but it is worth filing when the build is only just starting. A design approved in time stops being an issue; one filed late dictates the handover date.
What does a turnkey project like this include?
Design, permitting, supply, installation, commissioning and support through to certification, under a single contract and a single warranty.
Can CCTV and security be integrated into the same contract?
Yes, and it usually works out better. Coordinating electrical, network and security across three separate suppliers costs more management time than contracting them together.
Result

The outcome

The building was energised with its certification in order and the security systems running, free of the grey areas between designer, installer and certifier that appear when the work is contracted in pieces.

More projects in the construction sector →

Need something similar?

Tell us what you need and get a quote tailored to it. We advise you from the very first idea.